Contents
Migrating from Oracle to PostgreSQL is one of the most common scenarios for organisations looking to escape expensive vendor lock-in. An annual Oracle Enterprise Edition licence costs $47,500 per processor – before support. This guide covers the full journey to AWS (Aurora PostgreSQL or RDS PostgreSQL): tooling, challenges, realistic timelines, and how the AWS MAP programme can cover 70-80% of your migration partner's fees.

Executive summary – the numbers

  Simple (< 100 GB) Medium (100 GB – 1 TB) Complex / Enterprise
Timeline 4-8 weeks 8-14 weeks 14 weeks – 12 months
Project cost €23K – €46K €58K – €116K €116K – €700K
After MAP funding €7K – €14K €17K – €35K €35K – €210K
Annual Oracle licence savings $100K – $215K $215K – $430K $430K – $1M+
Payback period < 3 months < 4 months 3-6 months

MAP funding covers 70-80% of partner costs. A dedicated Oracle MAP track offers additional credits beyond the standard programme. Details below.

This guide is written for mid-market companies, enterprise IT, and public sector bodies across Europe and the US – organisations running multiple Oracle instances with complex PL/SQL logic that need to migrate without business disruption. We’ve delivered these projects for financial services firms in the City and Frankfurt, healthcare providers bound by NHS Digital standards, and Mittelstand manufacturers modernising legacy ERP backends.

If you need a broader AWS migration overview (not database-specific), see our complete AWS cloud migration guide.

 

Why organisations leave Oracle for PostgreSQL

Oracle licensing costs – the real scale

Component Annual cost (typical enterprise deployment)
Oracle Database Enterprise Edition $47,500/processor
Annual Support (22% of licence fee) $10,450/processor
Real Application Clusters (RAC) $23,000/processor
Partitioning Option $11,500/processor
Advanced Security $15,000/processor
Typical 2-socket server (2×8 cores = 16 cores × 0.5 factor) $107,450 – $214,900/year

For a mid-size deployment running two such servers, you’re looking at north of $400K per year in licensing alone – before hardware, DBAs, or data centre costs. Aurora PostgreSQL db.r6g.2xlarge (8 vCPU, 64 GB RAM, Multi-AZ) delivers comparable performance at ~$1,400/month = $16,800/year. No user limits. No audit exposure.

Oracle LMS audits – the single biggest trigger for migration decisions

Oracle License Management Services (LMS) audits are ruthless and increasingly common – particularly targeting organisations that have:

  • Virtualised their environment (VMware) without purchasing full-rack licensing
  • Run Oracle Standard Edition on servers with >2 sockets
  • Deployed RAC or Data Guard without the corresponding option licence

The typical outcome? A compliance demand of $500K–$2M+ in back-payments. We’ve seen UK financial services firms hit with seven-figure demands after VMware sprawl went unchecked. German Mittelstand companies face similar exposure, often triggered by Oracle’s push to audit ahead of contract renewals.

Migrating to PostgreSQL removes Oracle’s audit leverage entirely. No licence to be non-compliant with.

Vendor lock-in and inflexibility

  • Oracle licences per-processor – scaling up doubles your costs overnight
  • No consumption-based pricing (unlike Aurora PostgreSQL, which bills per-second)
  • Oracle on AWS still requires BYOL – you’ve moved to the cloud, but the licensing headache follows you
  • No native integration with AWS IAM, CloudWatch, or Secrets Manager without additional configuration layers

PostgreSQL – why the timing is right

PostgreSQL has matured dramatically. Version 16 handles table partitioning, parallel query execution, logical replication, and JSON/JSONB natively – capabilities that used to be Oracle’s moat.

On AWS specifically:

  • Aurora PostgreSQL delivers 3-5× standard PostgreSQL throughput with automatic failover and up to 15 read replicas. It’s a managed service – patching, backups, and HA are handled for you.
  • Native ecosystem integration – IAM database authentication, automatic secret rotation via Secrets Manager, Performance Insights for query-level observability
  • Zero licence cost – you pay for compute and storage, nothing else

For regulated industries (FCA in the UK, BaFin in Germany, or SEC-registered firms in the US), Aurora’s compliance certifications (ISO 27001, SOC 2, PCI DSS, C5 for DACH markets) mean you’re not trading Oracle compliance for a gap elsewhere.

 

Oracle vs PostgreSQL – key technical differences

Data type mapping

Oracle PostgreSQL Notes
NUMBER(p,s) NUMERIC(p,s) / INTEGER / BIGINT SCT maps automatically
VARCHAR2(n) VARCHAR(n) / TEXT TEXT in PostgreSQL has no performance penalty
DATE TIMESTAMP Oracle DATE includes time! PostgreSQL DATE does not
CLOB TEXT PostgreSQL TEXT has no 4 GB limit
BLOB BYTEA / Large Object BYTEA up to ~1 GB, Large Object for larger
RAW BYTEA
LONG TEXT Deprecated in Oracle, simple mapping
XMLTYPE XML Native XML type in PostgreSQL
INTERVAL YEAR TO MONTH INTERVAL PostgreSQL INTERVAL is more flexible
ROWID ctid (internal) Don’t rely on ROWID – use a primary key

PL/SQL vs PL/pgSQL – key syntax differences

Aspect Oracle PL/SQL PostgreSQL PL/pgSQL
Packages ✅ Native ❌ None – use schemas + extensions
Exceptions EXCEPTION WHEN EXCEPTION WHEN (similar syntax)
Cursors CURSOR, REF CURSOR, SYS_REFCURSOR CURSOR, REFCURSOR
Sequences sequence.NEXTVAL nextval(‘sequence’)
CONNECT BY (hierarchies) ✅ Native Use WITH RECURSIVE (CTE)
DECODE() ✅ Native Use CASE WHEN
NVL() ✅ Native COALESCE()
SYSDATE CURRENT_TIMESTAMP / NOW()
Autonomous transactions PRAGMA AUTONOMOUS_TRANSACTION dblink or pg_background (workaround)
Bulk operations FORALL, BULK COLLECT UNNEST + array operations
Materialized view refresh ON COMMIT / ON DEMAND CREATE MATERIALIZED VIEW + pg_cron

Oracle features without a direct equivalent

Oracle feature PostgreSQL alternative Migration complexity
Oracle RAC (multi-node clustering) Aurora Multi-AZ + read replicas Low (Aurora manages HA)
Oracle Data Guard Aurora Global Database / logical replication Low
Oracle Advanced Compression pg_lz4, TOAST compression, partitioning Medium
Oracle Flashback Point-in-time recovery (PITR) + pg_audit Low
Oracle MODEL clause Window functions + CTEs Medium (requires rewrite)
Oracle Database Links postgres_fdw / dblink Low
Oracle Advanced Queuing Amazon SQS/SNS or pg_notify Medium
Oracle Spatial PostGIS (extension) Low

 

Step-by-step migration – 8-phase process

Step 1: Assessment and conversion report (SCT)

Run AWS Schema Conversion Tool (SCT) against the source Oracle database. SCT generates an Assessment Report showing:

  • Percentage of objects that convert automatically (typically 60-85%)
  • List of objects requiring manual intervention (red/amber items)
  • Estimated effort for manual conversion

Output: A document categorising objects into auto-convert, simple-manual, and complex-manual. This forms the basis for project estimation.

Timeline: 2-5 days (depends on schema size)

Step 2: Choose the target engine – Aurora PostgreSQL vs RDS PostgreSQL

Criterion Aurora PostgreSQL RDS PostgreSQL
Performance 3-5× standard PG Standard
Storage Auto-scaling up to 128 TB EBS, manual scaling
HA Built-in Multi-AZ (6 copies across 3 AZs) Multi-AZ optional (+cost)
Read replicas Up to 15 Up to 15
Cost ~20% more than RDS Lower base cost
Failover 10-20 seconds 60-120 seconds
Recommendation Enterprise, large databases, HA requirements Smaller databases, dev/staging, cost-sensitive

For Oracle Enterprise Edition with RAC migrations: Aurora PostgreSQL is the natural choice – it delivers high availability without Oracle RAC complexity.

Step 3: Schema conversion

AWS SCT automatically converts:

  • Tables, indexes, constraints, sequences
  • Simple views and triggers
  • Stored procedures with basic logic

Manual conversion required for:

  • PL/SQL packages (PostgreSQL has no package equivalent – split into schemas + functions)
  • CONNECT BY hierarchies → WITH RECURSIVE CTE
  • Oracle built-in functions (DECODE → CASE, NVL → COALESCE)
  • Autonomous transactions
  • Advanced bulk processing (FORALL → array operations)

Tip: Don’t convert 1:1. It’s often better to rewrite procedures using native PostgreSQL features (window functions, LATERAL joins, array aggregation) rather than mimicking Oracle patterns.

AI-assisted conversion: LLM-based tools (Amazon Q Developer, GitHub Copilot) can translate 70-90% of SCT’s “red” objects – PL/SQL packages, CONNECT BY hierarchies, complex cursors. Engineers review and refine the output rather than writing from scratch. In our projects, this cuts the manual conversion phase by 40-60%.

Timeline: 1-4 weeks (depends on PL/SQL volume; with AI assistance, closer to the lower end)

Step 4: Data migration – AWS DMS

AWS Database Migration Service supports two modes:

Full load: One-time transfer of all data. Suitable for databases < 100 GB or where longer downtime (hours) is acceptable.

Full load + CDC (Change Data Capture): Initial full load followed by continuous change replication. Minimises downtime to minutes. Requires:

  • Oracle LogMiner or Binary Reader on the source
  • Supplemental logging enabled on Oracle
  • Appropriate privileges (EXECUTE_CATALOG_ROLE)

DMS configuration:

  • Replication instance: dms.r5.xlarge (minimum for production migrations)
  • Networking: VPN or Direct Connect to Oracle source
  • Table mapping: per-schema, with transformations (lowercase in PostgreSQL!)

Timeline: Full load 100 GB = 4-8 hours (depends on network). CDC lag: <5 seconds.

Step 5: Application code migration

Application changes that are almost always required:

  • Connection string: Oracle TNS → PostgreSQL libpq format
  • Driver: OCI/JDBC Oracle → npgsql/psycopg2/pg-promise
  • Case sensitivity: Oracle defaults to uppercase → PostgreSQL defaults to lowercase (unless quoted)
  • Sequence syntax: seq.NEXTVALnextval('seq')
  • DUAL table: SELECT 1 FROM DUALSELECT 1
  • Date handling: Oracle DATE includes time → PostgreSQL separates DATE and TIMESTAMP
  • Outer join syntax: Oracle (+) → ANSI LEFT/RIGHT JOIN
  • ROWNUM:LIMIT/OFFSET or window function ROW_NUMBER()

ORM-based applications (Hibernate, Entity Framework, Django): Changes are minimal – the ORM handles dialect differences. Configuration change + regression testing.

Raw SQL applications: Require a review of every query. Tools like orafce (a PostgreSQL extension emulating Oracle functions) can temporarily bridge differences.

Step 6: Testing and validation

Three layers of testing:

1. Data validation:

  • Row count comparison (source vs target)
  • Checksums on critical tables
  • Spot-check of random records
  • AWS DMS Data Validation task (automated)

2. Functional testing:

  • Run the full application regression test suite against the new database
  • Compare query results (Oracle vs PostgreSQL) for critical reports
  • Test stored procedures with edge cases

3. Performance testing:

  • Compare response times for the top 50 queries
  • Load testing with production traffic profile
  • Execution plan analysis – PostgreSQL’s optimiser behaves differently from Oracle CBO

AI-assisted validation: Generate test cases for stored procedures (based on schema and business logic), automate Oracle vs PostgreSQL result comparison on sample data, and identify performance regressions. LLMs analyse execution plans and suggest missing indexes. In practice, this shortens the testing phase by 30-40%.

Timeline: 2-4 weeks (don’t cut this short – it’s the most common point of project failure)

Step 7: Cutover – switching production

Near-zero-downtime strategy (DMS CDC):

  1. DMS replicates changes in real time (CDC lag <5s)
  2. Stop writes on Oracle (maintenance window)
  3. Wait for DMS to catch up to zero lag
  4. Switch application connection string to Aurora/RDS
  5. Validate – smoke tests
  6. Open traffic

Typical downtime: 5-30 minutes (time to drain lag + switch + smoke test)

Rollback plan: Keep Oracle in read-only mode for 48-72h after cutover. If a critical issue arises, rollback = switch the connection string back. DMS reverse replication is optional.

Step 8: Stabilisation and optimisation

First 2-4 weeks post-cutover:

  • Performance tuning: Adjust work_mem, shared_buffers, effective_cache_size to match workload profile
  • Index optimisation: PostgreSQL may need different indexes than Oracle (partial indexes, GIN indexes for JSONB)
  • Connection pooling: PgBouncer or RDS Proxy (Aurora has a max connections limit depending on instance class)
  • Monitoring: Performance Insights, Enhanced Monitoring, CloudWatch alarms on CPU, IOPS, connections
  • Oracle decommission: After 30 days of stable operation – shut down Oracle, cancel support contracts

 

AWS tools for Oracle → PostgreSQL migration

AWS Schema Conversion Tool (SCT)

SCT analyses your Oracle schema and generates equivalent PostgreSQL DDL plus PL/pgSQL procedures. Think of it as the first pass – it handles the straightforward conversions so your engineers can focus on the hard parts.

It generates a colour-coded Assessment Report: green means auto-converted, amber means you’ll need to tweak it, red means someone needs to sit down and think through the logic. In our experience, 60-85% of objects land in green or amber territory.

Where SCT falls short: PL/SQL packages get flattened (you lose encapsulation), CONNECT BY hierarchies need manual CTE rewrites, and some Oracle analytic functions require a human eye. But for the price (free – it’s part of the AWS toolkit), it’s an essential starting point.

AWS Database Migration Service (DMS)

DMS moves the actual data. It supports one-off full loads and, more importantly, continuous replication via Change Data Capture (CDC) – which is how you achieve near-zero downtime on the final cutover.

A few things to get right on the Oracle side: supplemental logging must be enabled, you’ll need Binary Reader or LogMiner access, and the replication instance should be sized at roughly 1 vCPU per 50 GB of data being loaded (or per 100 tables under CDC).

On the PostgreSQL target, set up a logical replication slot for Multi-AZ configurations and flip session_replication_role to replica during the initial load to avoid trigger interference.

Running cost is modest – roughly $0.018/h per vCPU on the replication instance, plus data transfer.

ora2pg – the open-source option

A Perl-based tool that handles schema and data conversion without any AWS dependency. Useful for smaller databases, on-premise PostgreSQL targets, or situations where you want fine-grained control over every conversion decision.

It’s less suitable for large enterprises with hundreds of stored procedures (SCT’s heuristics are better at scale) and it doesn’t support CDC – so you’ll still need DMS or a custom solution for live replication.

 

How AWS MAP funds your Oracle → PostgreSQL migration

What MAP actually is

The Migration Acceleration Program is AWS’s way of subsidising your move off competing platforms. It’s not a discount on AWS services – it’s funding that covers your migration partner’s fees (assessment, engineering, testing, cutover). Three phases, each with its own funding envelope:

Phase What gets funded Typical coverage
Assess Environment audit, business case, migration plan 50-100% of assessment costs
Mobilize Landing zone build, governance, proof of concept 50-80% of partner fees
Migrate & Modernize The actual migration work 70-80% of partner fees

The Oracle-specific MAP track

AWS runs a dedicated MAP track for Oracle database migrations with a larger budget than the standard programme. This isn’t widely advertised, but it exists because AWS has a strategic interest in moving Oracle workloads onto its platform.

What the Oracle track adds beyond standard MAP:

  • Additional credits to cover tooling, extended testing, and team upskilling
  • Higher funding ceilings for complex multi-database estates
  • “Windows of Opportunity” bonuses when you migrate before your Oracle renewal date (Oracle renewals are leverage points – AWS knows this)

Who qualifies

The bar isn’t as high as you might expect:

  • Active Oracle environment (on-premise, co-located, or running on EC2 with BYOL)
  • Minimum ~$50K in partner engagement value (this rules out trivial single-instance migrations, but most enterprise scenarios clear it easily)
  • Target must be an AWS-native database service (Aurora PostgreSQL or RDS PostgreSQL)
  • You need a certified MAP partner to submit the application. We handle this end-to-end.

What this looks like in practice

Scenario Project cost MAP covers You pay
Single Oracle SE instance, 50 GB, straightforward procedures €28,000 ~€19,000 (67%) ~€9,000
3× Oracle EE, 500 GB combined, complex PL/SQL €105,000 ~€74,000 (71%) ~€31,000
Enterprise estate: 10+ instances, 2+ TB, RAC clustering €280,000 ~€210,000 (75%) ~€70,000

On top of the partner fee coverage, you’ll typically receive 1-3 months of AWS infrastructure credits for the target environment, access to AWS Solution Architects during the project, and (for the largest engagements) direct involvement from AWS Professional Services.

DACH and UK compliance context

For organisations in regulated industries, MAP funding doesn’t change your compliance obligations – but Aurora PostgreSQL’s certification stack makes it easier to meet them:

  • UK (FCA-regulated): Aurora supports data residency in eu-west-2 (London). ISO 27001, SOC 2 Type II, and PCI DSS compliance certifications via AWS Artifact.
  • Germany/Austria/Switzerland (BaFin, FINMA): C5 attestation (BSI Cloud Computing Compliance Controls Catalogue) covers Aurora PostgreSQL. Data stays within eu-central-1 (Frankfurt).
  • GDPR/UK GDPR: Standard contractual clauses built into the AWS Data Processing Addendum. No data leaves the EU/UK unless you explicitly configure cross-region replication.

The qualification process

What we need from you to get started:

  1. Inventory of Oracle databases – instance count, sizes, rough procedure counts
  2. A business case outline – even back-of-envelope licensing savings vs migration cost
  3. Your Oracle renewal timeline – this determines urgency and can unlock bonus funding
  4. A conversation – we submit the MAP application on your behalf and manage the funding lifecycle through to completion

 

Most common Oracle → PostgreSQL migration challenges

1. Stored procedures with business logic

Problem: Enterprise Oracle databases have hundreds of PL/SQL procedures implementing business logic (calculations, validations, workflows). SCT converts 60-70% automatically; the rest requires manual work.

Solution:

  • Prioritise: identify procedures actually called in production (Oracle AWR report)
  • Rewrite, don’t translate: PostgreSQL has better window functions, CTEs and array operations – use them instead of mimicking Oracle
  • orafce extension: temporary bridge for Oracle-specific functions (NVL2, DECODE, LPAD with Oracle semantics)
  • Per-procedure testing: every converted procedure must pass testing with Oracle results as baseline
  • AI assistance (Amazon Q, Copilot): LLMs convert PL/SQL → PL/pgSQL with target schema context. Engineers verify and refine rather than writing from scratch. Reduces manual conversion effort by 40-60% and eliminates common syntax errors

2. Post-migration performance

Problem: Queries that ran in 50ms on Oracle can take 5s on PostgreSQL. Different optimiser, different statistics, different indexes.

Solution:

  • pg_stat_statements – identify the slowest queries
  • EXPLAIN (ANALYSE, BUFFERS) – compare execution plans
  • Additional indexes: PostgreSQL benefits from partial indexes, expression indexes, covering indexes
  • Tune random_page_cost (for SSD: 1.1 instead of the default 4.0)
  • Connection pooling: PgBouncer in transaction mode (Oracle handles thousands of connections natively; PostgreSQL needs a pooler)

3. Oracle-specific features without a direct equivalent

Problem: CONNECT BY, MODEL clause, MERGE with advanced logic, autonomous transactions.

Solution by feature:

Oracle feature PostgreSQL solution Effort
CONNECT BY WITH RECURSIVE CTE Low (pattern is straightforward, but needs testing)
MODEL clause Window functions + LATERAL Medium (requires understanding business logic)
MERGE (upsert) INSERT … ON CONFLICT Low
Autonomous transaction dblink to self or pg_background Medium (architecture change)
DBMS_SCHEDULER pg_cron or AWS EventBridge + Lambda Low
DBMS_OUTPUT RAISE NOTICE Low
UTL_FILE aws_s3 extension (Aurora) or COPY Low

4. DBA team mindset shift

Problem: Teams accustomed to Oracle (AWR, ASH, Enterprise Manager) need to learn new tooling.

Solution:

  • AWS Performance Insights = Oracle ASH (Active Session History) equivalent
  • pg_stat_statements = Oracle V$SQL equivalent
  • pgBadger = Oracle AWR Report equivalent
  • 2-3 day training for the DBA team (covered by MAP budget)

5. External integrations

Problem: Reporting systems (BI), ETL tools (Informatica, SSIS, Talend) and other applications connect directly to Oracle.

Solution:

  • Assessment phase identifies ALL connections to Oracle (netstat, AWR, Oracle auditing)
  • Cutover plan includes switching every integration
  • Parallel run: DMS maintains Oracle in read-only as a safety net for systems that can’t switch immediately

 

Timeline and costs for Oracle → PostgreSQL migration

By database size and complexity

Scenario Database size PL/SQL procedures Timeline Project cost With MAP
Simple < 100 GB < 50 simple 4-8 weeks €23,000 – €46,000
$25,000 – $50,000
€7,000 – €14,000
Medium 100 GB – 1 TB 50-200, some complex 8-14 weeks €58,000 – €116,000
$63,000 – $125,000
€17,000 – €35,000
Complex > 1 TB 200+, complex business logic 14-24 weeks €116,000 – €280,000
$125,000 – $300,000
€35,000 – €84,000
Enterprise multi-DB Multiple instances, 5+ TB total 500+, RAC, Data Guard 6-12 months €230,000 – €700,000
$250,000 – $750,000
€70,000 – €210,000

Costs above factor in AI-assisted code conversion (Amazon Q Developer, Copilot). Without AI tooling, the manual conversion phase would take 40-60% longer – particularly visible in “Complex” and “Enterprise” scenarios where stored procedure work dominates the budget.

What affects timeline

Factor Impact on timeline Why
PL/SQL volume +2-8 weeks per 100 complex procedures Manual conversion + testing
Zero-downtime requirement +2-3 weeks CDC setup, failover testing, parallel run
External integrations +1-3 weeks per 5 integrations Coordination with external teams
No regression tests +3-4 weeks Must write tests from scratch
Multi-region target +2-4 weeks Aurora Global Database setup, DR testing

Post-migration savings – ROI

Typical organisation with 2 Oracle EE instances (2-socket each):

Line item Oracle (annual cost) Aurora PostgreSQL (annual cost) Saving
Licence + support $215,000 × 2 = $430,000 $0 $430,000
Infrastructure $48,000 (on-premise servers) $40,000 (2× db.r6g.2xlarge Multi-AZ, RI) $8,000
DBA effort $120,000 (1.5 FTE) $80,000 (1 FTE – less manual work) $40,000
Annual total $598,000 $120,000 $478,000/year

At a migration cost of ~€70,000 after MAP funding – ROI in under 4 months.

 

Frequently asked questions

How long does an Oracle to PostgreSQL migration take?

From 4-8 weeks for simple databases (< 100 GB, minimal PL/SQL) to 6-12 months for enterprise with multiple instances, complex business logic in stored procedures, and zero-downtime requirements. The most common scenario (medium database, 100 GB – 1 TB) takes 8-14 weeks.

Does AWS SCT convert PL/SQL automatically?

AWS SCT automatically converts 60-85% of schema objects (tables, indexes, simple procedures). Complex PL/SQL constructs (packages, CONNECT BY, autonomous transactions, MODEL clause) require manual conversion. SCT generates an Assessment Report that precisely identifies what needs manual work.

How much does Oracle to PostgreSQL migration cost?

Project costs range from €23,000 to €700,000 depending on database size and PL/SQL complexity. AWS MAP funding covers 70-80% of partner costs, reducing effective cost to €7,000 – €210,000. Annual Oracle licence savings typically run $200,000 – $500,000 – delivering ROI within 3-6 months.

Does migration require downtime?

No. Using AWS DMS with CDC (Change Data Capture), migration happens with minimal downtime of 5-30 minutes – the time needed to drain the final changes and switch the connection string. DMS replicates changes in real time with lag under 5 seconds.

Aurora PostgreSQL or RDS PostgreSQL – which to choose after Oracle migration?

Aurora PostgreSQL for enterprise: 3-5× standard PG performance, automatic failover in 10-20s, storage up to 128 TB, up to 15 read replicas. RDS PostgreSQL for smaller databases and dev/staging environments where lower base cost is the priority. For Oracle Enterprise Edition with RAC migrations, Aurora is the natural equivalent.

What is AWS MAP and how does it help with Oracle migration?

AWS Migration Acceleration Program (MAP) is a funding programme covering 70-80% of migration partner engagement costs. For Oracle migrations, a dedicated track exists with an increased budget. Organisations with active Oracle environments migrating to AWS services (Aurora/RDS PostgreSQL) qualify. A MAP partner (e.g. Devopsity) submits the application and manages the budget on the client’s behalf.

 

Next steps – free migration assessment

Every Oracle → PostgreSQL migration starts with assessment. We analyse your Oracle estate (schemas, PL/SQL complexity, data volumes, integration points) and come back with:

  1. SCT conversion report – what converts automatically, what needs engineering time
  2. Cost and timeline estimate – realistic ranges, including MAP funding projections
  3. Architecture recommendation – Aurora vs RDS, Multi-AZ, read replicas, pooling strategy
  4. Cutover plan – how to switch with minimal business disruption

We’ve delivered Oracle exits for regulated firms in London, Frankfurt, and across the Nordics. Whether you’re facing an Oracle renewal in six months or an LMS audit demand letter on your desk, the first step is understanding what you’re working with.

Jerzy Kopaczewski

Considering leaving Oracle?

Book a free 30-minute call. We'll assess your migration complexity and check whether your project qualifies for AWS MAP funding (typically 70-80% of costs covered).

AWS database migration Oracle PostgreSQL Aurora PostgreSQL AWS DMS AWS SCT AWS MAP

Read also:

Previous post Next post